New PPM Function: TotalFloat

by Product Marketing

February 14, 2022

TotalFloat() function calculates the number of working days that a task can be delayed without impacting the Project Finish Date. This new formula function will help project, program, and portfolio managers more effectively identify and mitigate risk in large-scale, dependency enabled project sheets.

Note: If dependencies are not enabled, you may see #INVALID COLUMN VALUE error. 

Download the Formula Examples template in the Solution Center to see examples of each Smartsheet function in action. Learn more.

Environments availability: Commercial US, Commercial EU

Plan type availability: Individual, Pro, Business, Enterprise